Concrete coating and installation of subsea pipe line for phase 6, 7 & 8 south pars

Year: 2006

 

Concrete Coating & Installation of Subsea Pipe Line for Phase 6, 7 & 8 South Pars

 

Client: Statoil

 

Length: 310 Km, 32″

 

 

This project included application of anticorrosive, weight coating and installation of cathodic protection of the following subsea pipelines, execution of the temporary works for pipeline shore approach (winch installation, etc.) on the beach for pipelines installation.

 

Three 32″ multiphase sea-lines, which would be carbon steel API 5L, with approximate length of 95.4, 101.8 and 110.6 Km for phase 6, 7 & 8 respectively, plus 4Km of land section for each phase.