Installation of Hengam Field Jacket E4 & E2

Year: 2011

Installation of Hengam Field Jacket E4 & E2

Pile Driving and Grouting

E4: 2000 Ton, 84 m

E2: 1600 Ton, 81 m

It was used the 7000 tones capacity of LB 90 (Launch Barge)

The SADAF Company was awarded a contract for the installation of two jackets (E2 & E4) and for the first time successfully used their 7000 ton capacity launch barge LB 90 for the individual transportation and launch of both jackets.

The scope of work included pile driving & grouting of the 84 meter, 2000 tone (E4) and 81 meter, 1600 tone (E2) structures.